"What's your lead time?" Ask that, and most people get back a single number: "30 days."
That number means almost nothing, because three things have not been settled: the day the clock starts, what the 30 days include, and what happens if it runs late.
First: the Day the Clock Starts
The same "30 days" can end two or three weeks apart in practice, depending on the starting point:
| Starting point | What it actually means |
|---|---|
| Deposit received | The most common — but confirm "received", not "sent" |
| Sample approved | If the sample still has to be revised, the 30 days only count from the revised one |
| Raw material at the factory | In peak season, when material is tight, this one line can push the lead time back a long way |
The question you must ask: "30 days from which day?" And get the answer into the PI.
A common trap: the contract says "30 days after the deposit is received", and once the deposit lands the other side says "the material hasn't arrived yet" — and the delay has become open-ended.
Second: What the 30 Days Include
A complete lead time should cover four stages. Many quotations include only the first:
- Production (the time actually spent on the line);
- Packing (inner packing + outer carton + labelling);
- Inspection (you or a third party come to look, usually 1–2 days);
- Delivery to warehouse / port (factory to the named point; in peak season, leave a buffer).
How to ask: "Does this lead time include packing and delivery to warehouse? Where does inspection sit in the schedule?"
If it covers production only, add one to two weeks to the date you actually have the goods in hand.
Third: What Happens if It Runs Late
A lead time without a late-delivery clause is a wish.
Three things have to be written down:
① A grace period. A few days late is not a breach (3–7 days is common practice); only beyond that counts.
② The consequence. A deduction per day late, or a percentage off the price — the figure is for the two sides to agree, but it has to be written.
③ The line at which you may cancel. Beyond how many days late you can cancel the order and ask for the deposit back.
Leave those three out, and a delay is just "sorry about that".
How to Negotiate: Three Methods You Can Use Right Away
① Ask for the production schedule, not a number.
Ask "can you give me a production schedule" — and you get "material on this day, production starts on this day, finished on this day". That is far more reliable than "30 days", because a schedule is a commitment and a number is an estimate.
② Split shipment.
On a large order, split one order into two lots: the first lot goes out, the second follows. Then even a delay hits only part of the goods. The cost is one more freight charge and one more customs declaration.
③ Build in a buffer of your own.
Do not promise your customer what the factory told you — 30 days. Promise 30 days plus a one-week buffer, and you will sleep.
One Counter-Intuitive Point
Shorter is not better.
A factory willing to say "45 days" is often more reliable than one that confidently promises "25" — because the first has worked out a schedule, and the second is just chasing the order.
How to tell: ask "why 45 days". The one who can answer "7 days for material + 30 days production + 8 days packing and delivery to warehouse" has actually done the arithmetic.
One Test
A lead time is a negotiation about three things, not one:
- The starting point (which day the clock starts);
- What is included (packing, inspection, delivery to warehouse — in or out);
- The consequence of delay (grace period, deduction, right to cancel).
With all three in the PI, the lead time is a commitment. With one number only, it is an estimate.