Buying from China: When Factories Stop

Plan around two calendars: Spring Festival 2026 runs 9 days, Yiwu's market closes 10 working days, factories restart at 61.4%. Book by sailing schedule.

For Spring Festival 2026 the General Office of the State Council set the holiday at 9 days, February 15 to February 23. The market closure notice for Yiwu International Trade City names a different window: shut on the afternoon of February 13, reopening at 8:30 a.m. on February 28. Factories and markets actually stop for more than two weeks, not for those 9 days. Anyone who books flights around the statutory holiday lands on a row of rolled-down shutters.

1. The official notice: 9 days, with two Saturdays turned into workdays

The Notice of the General Office of the State Council on the Arrangement of Some Public Holidays in 2026 (Guobanfamingdian [2025] No. 7), dated November 4, 2025, reads: the Spring Festival holiday runs from February 15 (the 28th day of the 12th lunar month, a Sunday) to February 23 (the 7th day of the 1st lunar month, a Monday), 9 days in total, with adjusted rest days; February 14 (Saturday) and February 28 (Saturday) are working days. The first day of the 1st lunar month falls on February 17, a Tuesday. The 9 days include three weekend days — February 15, 21 and 22 — while the two Saturdays, February 14 and February 28, are working days under the notice.

The same notice cuts the year into seven blocks: New Year's Day 3 days, Spring Festival 9 days, Qingming 3 days, Labor Day 5 days, Dragon Boat 3 days, Mid-Autumn 3 days, National Day 7 days. In 2026 only Spring Festival and National Day cover a full working week. One line at the end of the notice is often skipped: it asks employers to combine the holiday with paid annual leave so that a longer break forms and travel staggers. How much room that flexibility leaves on paper becomes clear from the Yiwu timetable.

2. The Yiwu timetable: closed on the afternoon of the 13th, open on the morning of the 28th

The market closure and reopening notice issued by Zhejiang China Commodities City Group on February 2, 2026 is precise. The Global Digital Trade Center, Yiwu International Trade City Districts 1 to 5, the International Production Materials Market and the indoor halls of the Binwang 158 Cultural and Creative Park close on the afternoon of February 13 (the 26th day of the 12th lunar month), and reopen at 8:30 a.m. on February 28 (the 12th day of the 1st lunar month). Reopening does not happen in one day for everything: the Imported Goods City in District 5 and the Huangyuan Garment Market close on February 14, and the Imported Goods City reopens at 10 a.m. on February 19 (the 3rd day of the 1st lunar month), 9 days ahead of the main market.

Count against the calendar: the official holiday falls on February 16 to 20 and February 23, 6 working days; the market is closed on February 16 to 20 and February 23 to 27, 10 working days. The 4 extra working days appear in no holiday notice. Of the two Saturdays converted into working days, the market is closed on one (February 14) and open on the other (February 28).

3. Factories reopen later than the holiday ends

According to a Jinhua Daily report on March 2, 2026, as of February 26 (the 10th day of the 1st lunar month) the resumption rate among above-scale industrial enterprises across Jinhua stood at 61.4%, and the production recovery rate at 51%. The official holiday ended on February 23; by February 26 three working days had passed, close to 40% of above-scale enterprises had still not resumed work, and just over half had restored production. The two figures say the same thing: machines are turning, lines are not full.

In the same report, one garment maker in Yiwu ran on this rhythm: work starts on the 8th day of the 1st lunar month, half the automated lines run by the 10th day, the whole line by the 12th day. In the week after the holiday the plant is starting machines, not shipping goods. The opposite sample exists too: 14 key enterprises in the Yiwu Economic Development Zone kept producing through Spring Festival, and 89 enterprises across Jinhua did the same, so shutdowns have to be asked about plant by plant; counting by city gives the wrong answer.

4. Ships leave before factories open

Carriers publish their Spring Festival schedules earlier than factories issue resumption notices. According to shipping trade media including Shipping Network, the Gemini alliance (Maersk and Hapag-Lloyd) scheduled a large number of blank sailings for Spring Festival 2026: with the lunar new year on February 17, 16 sailings were cancelled across the alliance network, touching trans-Pacific, Europe, the Arabian Gulf and South America East Coast services. Hapag-Lloyd's suspensions hit 7 services from Asia to the United States and 5 from Asia to Europe. MSC also cancelled multiple Asia–North Europe, Mediterranean and United States sailings over the same period. Carriers gave reduced export activity during the holiday as the reason.

For a buyer this means one thing: goods finished in mid-February may not have a ship, and a ship does not guarantee space. This bottleneck has nothing to do with whether a factory is open; it is a separate line. Booking therefore follows sailing schedules, not factory lead times.

5. Lead times are not guesses

Crane Worldwide Logistics' 2026 Lunar New Year shipping guide gives the timetable: book FCL and LCL ocean freight 3–5 weeks before the holiday, reserve air capacity 2–3 weeks before, expect drayage to the port to tighten 10–14 days before, and allow 1–2 weeks or more for the post-holiday backlog. These numbers are not recommendations; they are positions in a queue. Those at the back are the first to be dropped when carriers cut sailings.

Work backwards: to have goods finished, warehoused and loaded before the market closes on February 13, booking has to be done in January. To catch the first post-holiday sailings, accept that the market only reopens on February 28 and that factories need another one to two weeks to reach full output. There is no third route between the two windows.

6. February, in five segments

PeriodMarketFactoriesWhat is possible
Before February 13OpenNormalInspect goods, book, ship
Afternoon of February 13 to February 18Main market closedShutting down one by oneCalls, WeChat, confirm production scheduling
February 19 to February 23Only the Imported Goods City openOn holidayThe Imported Goods City can be visited, the main market cannot
February 24 to February 27ClosedStaff returning, output below fullConfirm resumption dates, schedule the first post-holiday batch
From February 28Reopens at 8:30 a.m.Ramping to full outputInspect, place orders, ship

The table holds only for 2026; lunar dates move every year and have to be checked again next year. Book flights by the State Council table and schedule delivery by the market reopening table. The two weeks in which the two tables disagree are the two weeks to plan around in this particular year.